CMSD’s master facilities plan with the OFCC is completed in segments. Segments 1-7 have been completed, resulting in a total of 43 new and 8 renovated school buildings. The project agreement for Segment 8 was approved in August 2021 and includes 3 new school buildings and 1 school renovation. Segment 8 school buildings are scheduled to be completed by Spring 2025.
Segment 1 SCHOOLS
New build 2003
Formerly East High School; Renovated 2003
Renovated 2004
New build 2005
New build 2005
Renovated 2006
New build 2006
New build 2007
Segment 2 SCHOOLS
Segment 3 SCHOOLS
New build 2009
New build 2009
New build 2009
New build 2009
New build 2009
New build 2009
New build 2009
New build 2009
New build 2010
Segment 4 SChools
New build 2010
New build 2010
New build 2010
New build 2010
New build 2010
New build 2010
New build 2010
New build 2011
New build 2011
Segment 5 Schools
Segment 6 School
New build 2017
Segment 7 Schools
New build 2018
New build 2018
New build 2018
New build 2018
New build 2018
New build 2018
New build 2019
New build 2020
New build 2020